Fort Smith, AR
Home MenuContact
Water/Sewer Emergency
479-784-2342
Citizen Services
623 Garrison Avenue, Room 101
Fort Smith, AR 72901
Government » Departments » Engineering
Utility Projects
(Non Consent Decree)
Water Projects Under Construction
Contractor
Forsgren, Inc.
Designer/Engineer
Hawkins-Weir Engineers, Inc.
Estimated Completion Date
9/04/2026
Total Project Cost
$15,783,939.50
Scope of Work
The scope of this project consists of the relocation of water and sewer utilities along the entire length of the ARDOT Highway 45 Widening Project.
Contractor
Crawford Construction Company
Designer/Engineer
Burns & McDonnell Engineering Company, Inc.
Estimated Completion Date
12-29-2025
Expected Project Cost
$2,213,560.00
Scope of Work
This project involves the open cut installation of approximately 736 linear feet of concrete encased 66-inch steel casing pipe under the I-49 on and off ramps. The work will be done without impacting traffic, and in advance of the future construction of the 48" water transmission line.
Contractor
N/A
Designer/Engineer
Burns & McDonnell Engineering Company
Estimated Completion Date
N/A
Total Project Cost
$2,707,866.00
Scope of Work
The City has begun constructing a new 48-inch water transmission line that will cover over 30 miles from the Lake Fort Smith Water Treatment Plant located in Mountainburg to Fort Smith. The new line will replace the original 27-inch water transmission line constructed in the 1930s. This project will be implemented in phases and is planned for completion in 2025. The larger diameter line will allow the amount of water supplied to the region’s water users to increase from 34 MGD to 70 MGD. It will also improve the level of service to the south and east sides of Fort Smith.
Phase II is currently under design. This phase will extend the transmission line an additional 12 miles from the end of Phase I to a location near the intersection of Rudy Road and Old Dollard Way.
Previous Phases
Phase I of this project is complete. Approximately six miles of the transmission line was installed from the Lake Fort Smith Water Treatment Facility in Mountainburg to a location near the intersection of S.H. 282 and I-49.
Contractor
N/A
Designer/Engineer
Burns & McDonnell Engineering Company
Estimated Completion Date
N/A
Total Project Cost
$25,000,000 (EST.)
Scope of Work
The City has begun constructing a new 48-inch water transmission line that will cover over 30 miles from the Lake Fort Smith Water Treatment Plant located in Mountainburg to Fort Smith. The new line will replace the original 27-inch water transmission line constructed in the 1930s. This project will be implemented in phases and is planned for completion in 2025. The larger diameter line will allow the amount of water supplied to the region’s water users to increase from 34 MGD to 70 MGD. It will also improve the level of service to the south and east sides of Fort Smith.
Phase III of this project will extend the transmission line from the end of Phase II to Gun Club Road / Levee Road near the Highway 59 crossing of the Arkansas River. This phase is currently under design and will consist of approximately 10 miles of 48-inch pipe.
Previous Phases
Phase I of this project is complete. Approximately six miles of the transmission line was installed from the Lake Fort Smith Water Treatment Facility in Mountainburg to a location near the intersection of S.H. 282 and I-49.
Phase II is currently under design. This phase will extend the transmission line an additional 12 miles from the end of Phase I to a location near the intersection of Rudy Road and Old Dollard Way.
Contractor
N/A
Designer/Engineer
Burns & McDonnell Engineering Company
Estimated Completion Date
N/A
Total Project Cost
$733,042.00 (Design Only)
Scope of Work
The City has begun constructing a new 48-inch water transmission line that will cover over 30 miles from the Lake Fort Smith Water Treatment Plant located in Mountainburg to Fort Smith. The new line will replace the original 27-inch water transmission line constructed in the 1930s. This project will be implemented in phases and is planned for completion in 2025. The larger diameter line will allow the amount of water supplied to the region’s water users to increase from 34 MGD to 70 MGD. It will also improve the level of service to the south and east sides of Fort Smith.
Phase IV of the transmission line will extend the transmission line from the end of Phase III to H Street in Barling. This phase, currently under design, is expected to include approximately 2.2 miles of 48-inch pipe and cross under the Arkansas River.
Previous Phases
Phase I of this project is complete. Approximately six miles of the transmission line was installed from the Lake Fort Smith Water Treatment Facility in Mountainburg to a location near the intersection of S.H. 282 and I-49.
Phase II is currently under design. This phase will extend the transmission line an additional 12 miles from the end of Phase I to a location near the intersection of Rudy Road and Old Dollard Way.
Phase III will extend the transmission line from the end of Phase II to Gun Club Road / Levee Road near the Highway 59 crossing of the Arkansas River. This phase is currently under design and will consist of approximately 10 miles of 48-inch pipe.
Contractor
N/A
Designer/Engineer
Burns & McDonnell Engineering Company
Estimated Completion Date
2025
Total Project Cost
$1,032,685.00 (Design Only)
Scope of Work
The City has begun constructing a new 48-inch water transmission line that will cover over 30 miles from the Lake Fort Smith Water Treatment Plant located in Mountainburg to Fort Smith. The new line will replace the original 27-inch water transmission line constructed in the 1930s. This project will be implemented in phases and is planned for completion in 2025. The larger diameter line will allow the amount of water supplied to the region’s water users to increase from 34 MGD to 70 MGD. It will also improve the level of service to the south and east sides of Fort Smith.
Phase V of this project will extend the transmission line from the end of Phase IV to a point near the intersection of Zero Street (Hwy 255) and Massard Road. This phase will complete the 48-inch transmission line connection to the Fort Smith distribution network.
Previous Phases
Phase I of this project is complete. Approximately six miles of the transmission line was installed from the Lake Fort Smith Water Treatment Facility in Mountainburg to a location near the intersection of S.H. 282 and I-49.
Phase II is currently under design. This phase will extend the transmission line an additional 12 miles from the end of Phase I to a location near the intersection of Rudy Road and Old Dollard Way.
Phase III will extend the transmission line from the end of Phase II to Gun Club Road / Levee Road near the Highway 59 crossing of the Arkansas River. This phase is currently under design and will consist of approximately 10 miles of 48-inch pipe.
Phase IV will extend the transmission line from the end of Phase III to H Street in Barling. This phase, currently under design, is expected to include approximately 2.2 miles of 48-inch pipe and cross under the Arkansas River.
Wastewater Projects Under Construction
Contractor
TBD
Designer/Engineer
TBD
Estimated Completion Date
TBD
Total Project Cost
$TBD
Scope of Work
TBD
Completed Projects
Contractor
Van Horn Construction, Inc.
Designer/Engineer
Hawkins – Weir Engineers, Inc.
Project Completion Date
06/06/23
Total Project Cost
$6,067,180.16
Scope of Work
Project 19-29-C4 was part of the overall 19-29 project to evaluate and repair sanitary sewer pump stations damaged in the 2019 flood. This project included Pump Station 20 at Fort Smith Park adjacent to North 6th St and Pump Station 21 at South 98th Circle. Following evaluation, it was determined that both pump stations required complete replacement.
Pump Station 28 and Pump Station 29 were constructed to replace the damaged stations as part of the Construction Management At-Risk Agreement with Van Horn Construction, Inc. The agreement had a Guaranteed Maximum Price (GMP) of $6,205,125.00. The project was completed with a final cost of $6,067,180.16, which is $137,944.84 less than the original GMP. The funding for the project was available through the 2018 Revenue Bond and will be submitted to FEMA for reimbursement.
Contractor
Goodwin & Goodwin, Inc.
Designer/Engineer
Hawkins – Weir Engineers, Inc.
Project Completion Date
06/03/2023
Total Project Cost
$1,949,835.00
Scope of Work
This project extended a 12-inch water line along Riverfront Drive (State Hwy 255) from P Street to Spradling Avenue. Additionally, a sewer pump station and around 600 feet of sewer force main were installed to support an RV Park currently under construction approximately 500 feet north of the Riverfront Drive and P Street Intersection.
Contractor
Crawford Construction Company
Designer/Engineer
Hawkins – Weir Engineers, Inc.
Project Completion Date
8/16/2023
Total Project Cost
$732,469.41
Scope of Work
The scope of this project included the extension of the City of Fort Smith Lee Creek Transmission Line’s 68-inch diameter steel encasement pipe to facilitate the construction of I-40/Hwy 59 Interchange Improvements by the Arkansas Department of Transportation, Job No. 040714.
The project was completed earlier than expected and at 3.05% less than the original contract amount. The funding for this project is available through the 6505 Capital Improvement Fund and will be reimbursable by ARDOT.
Contractor
Forsgren, Inc.
Designer/Engineer
N/A
Project Completion Date
12/31/2023
Total Project Cost
$2,629,541.37
Scope of Work
This project included the repair of leaking 1-inch and 2-inch water service lines, including new taps on the main water lines, and the installation of new water meter boxes. 619 water leaks were repaired over the course of two years at an average cost of $4,248 per leak. This project was funded through the Capital Improvement Fund.
Contractor
Forsgren, Inc.
Designer/Engineer
Halff Associates
Project Completion Date
9/26/2025
Total Project Cost
$925,494.52
Scope of Work
The scope of this project included the relocation of an 18” water transmission line to accommodate an Arkansas Department of Transportation (ARDOT) project to widen Arkansas State Highway 255. The majority of the project is 100% reimbursable by ArDOT, with the exception of the water valve modifications which will be reimbursed at 67.51%. This project aligns with the goals of the comprehensive plan policy TI5.2, ensuring that utility and infrastructure systems can meet the city’s long-term needs.
Contractor
Crawford Construction Company
Designer/Engineer
Burns & McDonnell Engineering
Completion Date
08/09/2024
Total Project Cost
$593,715.50
Scope of Work
This project consisted of an open-cut installation of approximately 328 linear feet of concrete-encased 66-inch steel casing pipe, in two locations, in preparation of future water transmission line installation. The work was required to be completed prior to construction of I-49 and is 100% reimbursable by ARDOT.
Contractor
Vortex Services, LLC
Designer/Engineer
In-House
Completion Date
July 30, 2024
Total Project Cost
$1,108,981.31
Scope of Work
This project replaced 350 linear feet of a 10-inch sanitary sewer main and two manholes The work took place between North I St. and North J St., in the alley between N 8th St. and N 9th St., where a segment of the main had collapsed. The collapse had previously caused a sinkhole and a Sanitary Sewer Overflow (SSO).
The funding for this project is available through the 6505 Excess Sales and Use Tax.
Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.
Windows Media Player
Word Viewer
Excel Viewer
PowerPoint Viewer
